Design Phase

Plan Review and Approvals

Acceptance testing quick reference

All tests per NFPA 13, Chapter 27. Confirm AHJ requirements before scheduling — some jurisdictions add tests or modify criteria.

TestRequirementDurationAcceptance Criteria
Hydrostatic (wet pipe)200 psi or 50 psi above max working pressure, whichever is greater2 hoursNo visible leaks, no pressure drop
Hydrostatic (dry pipe)200 psi or 50 psi above max working pressure2 hoursNo visible leaks, no pressure drop
Air test (dry/preaction, pre-2019)40 psi24 hoursMax 1.5 psi drop
Air test (dry/preaction, 2019+)System operating pressure2 hoursMax 3 psi drop
Main drain testFully open main drain, record static and residualN/ACompare to original flow test data
Inspector's testOpen most remote inspector's test connectionN/AWaterflow alarm activates within 90 seconds
Trip test (dry valve)Trip the dry valveN/AWater to inspector's test in 60 seconds
Trip test (preaction)Activate detection and trip valveN/AWater delivery per system design
Alarm testActivate all alarm devicesN/AAll alarms received at FACP and central station
Antifreeze testVerify solution concentrationN/AConcentration within listed range (refractometer)

Hydrostatic test pressure must be maintained for the full 2 hours. If the system cannot hold pressure, do not attempt to compensate by re-pumping during the test. Find and fix the leak.

Test preparation checklist:

  • [ ] All piping complete and supported
  • [ ] All heads installed (or test plugs in place with AHJ approval)
  • [ ] FDC connections capped
  • [ ] Gauges installed at riser and at test location
  • [ ] Drain path established for inspector's test
  • [ ] FACP and monitoring in place for alarm tests
  • [ ] AHJ and/or third-party inspector scheduled

FM Global vs. NFPA 13 — key differences

Projects with FM Global insurance often have requirements that exceed NFPA 13. Identify FM involvement early.

RequirementNFPA 13FM Global
Governing documentsNFPA 13 standardFM Data Sheets (DS 2-0, 3-26, 8-9, etc.)
Design densityPer standard tables/curvesOften higher than NFPA 13, especially for storage
Storage protectionChapters 20-26DS 8-9 — frequently more conservative
Water supply safety margin10 psi typical practiceMay require 15-25 psi margin depending on data sheet
Component approvalUL ListedFM Approved (separate listing)
Sprinkler headsAny UL listed head meeting designFM Approved heads required — not all UL heads are FM Approved
Rack storageIn-rack per NFPA 13 tablesDS 8-9 may require additional in-rack levels
Hydraulic calculationsNFPA 13 methodologySame methodology, but higher demand points
Inspection frequencyNFPA 25FM may require more frequent inspections
Plan reviewAHJ reviewFM engineering review in addition to AHJ

FM Approved is not the same as UL Listed. A head can be UL Listed but not FM Approved. Always verify component approval status when FM Global is the insurer.


Common plan review rejection reasons

Rejection ItemResolution
Flow test data expired (> 12 months)Obtain new flow test per NFPA 291
Hydraulic calc summary missing or incompleteInclude demand point, supply curve, safety margin, and node-by-node results
Head spacing exceeds listingVerify against cut sheet; add or relocate heads
Obstruction rules not addressedApply Section 8.5.5; show obstruction analysis on plans
Seismic bracing missing in required zoneAdd bracing per Section 18.5; show on plans with calculations
Hanger spacing exceeds tableAdd hangers per Table 9.2.1
Inadequate water supplyIncrease pipe sizes, reduce friction loss, or request fire pump
Wrong hazard classificationProvide occupancy documentation; re-classify per Chapter 5
Missing alarm device detailsShow all waterflow switches, tamper switches, and FACP connections
Plans not signed/sealedObtain required professional signature per state licensing requirements
No commodity classification for storageClassify per NFPA 13 Section 5.6; document on plans
Design area not shown on plansOutline the hydraulically most remote area with dimensions

AHJ submittal requirements

Minimum submittal per NFPA 13 Chapter 29:

ItemRequired Content
Floor plansAll piping with sizes, head locations, hanger locations, brace locations, valve locations
Riser diagramValve arrangement, trim, component identification, connection to water supply
Hydraulic calculationsComplete node-by-node, with summary and supply/demand graph
Water supply dataFlow test with static, residual, and flow; date and location
Cut sheetsEvery head, valve, and device used in the system
Material listPipe type, fitting type, hanger type, and quantities
System descriptionHazard classification, design criteria, occupancy type, building construction
Seismic dataSeismic design category, bracing calculations, brace locations (if applicable)

Supplemental items that reduce review time:

  • Cover sheet with project info, contractor license, and point of contact
  • Code edition and any local amendments referenced
  • Previous review comments with responses (for re-submittals)
  • Color-coded revisions for re-submittals

Acceptance testing procedures

Hydrostatic test — step by step

  1. Close the main control valve
  2. Connect test pump to the system (through FDC or test connection)
  3. Fill system completely — all air must be vented from high points
  4. Pump to test pressure (200 psi or 50 psi above max WP)
  5. Close pump valve and record gauge reading
  6. Wait 2 hours
  7. Record final gauge reading
  8. Walk all piping looking for visible leaks
  9. Pass: no visible leaks and no pressure drop on gauge
  10. Document results on test certificate

Temperature changes during testing affect pressure readings. A 10F temperature increase can raise pressure by approximately 10 psi in a closed system. Account for ambient conditions when evaluating results.

Main drain test

  1. Record static pressure at the system gauge
  2. Fully open the main drain valve
  3. Wait for pressure to stabilize (minimum 30 seconds)
  4. Record residual pressure
  5. Close drain valve
  6. Compare static and residual to the original flow test data
  7. A significant drop from original values indicates a water supply problem

Inspector's test (wet systems)

  1. Open the inspector's test connection at the hydraulically most remote point
  2. Start a timer when the valve opens
  3. Waterflow alarm must activate within 90 seconds
  4. Verify alarm signal is received at the FACP
  5. Verify alarm signal is transmitted to the central monitoring station
  6. Close the test connection
  7. Verify the system resets properly

As-built documentation requirements

Per NFPA 13, as-built drawings must reflect actual installed conditions. This is a code requirement, not optional.

As-built drawings must show:

  • [ ] All installed piping with actual sizes (including any field changes)
  • [ ] All sprinkler head locations as installed
  • [ ] All valve locations with identification numbers
  • [ ] All hanger and brace locations as installed
  • [ ] Any deviations from the approved plans — clearly marked
  • [ ] Actual pipe lengths if they differ from approved plans
  • [ ] Any field-routed piping not shown on original plans

As-built documentation package:

DocumentRecipient
As-built drawingsBuilding owner and AHJ
Hydraulic calculations (updated if design changed)Building owner and AHJ
Test certificates (hydrostatic, alarm, drain)Building owner and AHJ
Contractor's material and test certificate (NFPA 13 form)Building owner and AHJ
Sprinkler head and device cut sheetsBuilding owner
Spare head cabinet inventoryBuilding owner
Operating instructions for valves and devicesBuilding owner

The spare head cabinet must contain a minimum of 6 spare heads for systems with under 300 heads, 12 for 300-1000, and 24 for over 1000 heads. Include a sprinkler wrench for each head type. This is an NFPA 13 requirement, not a suggestion.


Inspection, testing, and maintenance handoff

At project closeout, the installing contractor should provide the building owner with:

ItemPurpose
NFPA 25 summaryInspection, testing, and maintenance schedule for all system components
Valve location chartQuick reference for emergency shutdowns
Spare head cabinet locationSo maintenance staff can find it
Fire pump operation manualIf applicable — includes test procedures
Monitoring company contact infoCentral station and local alarm company
Contractor contact infoFor service, repairs, and warranty issues

Many building owners do not understand their NFPA 25 obligations. A brief handoff meeting explaining the inspection schedule prevents system neglect and potential liability for the installing contractor.

Previous
Coordination with Other Trades